Which of the following checkpoints would be appropriate?

Topic 16, Scenario 10, V1 "Online Application"

There is a formal requirement from the business to develop an additional on-line application to the company website which will allow existing policyholders to extend their cover for short-term foreign use of their vehicle overseas. The current manual process will be retained. The application must be implemented in months time in line with the marketing department’s green initiative, which is anticipated to generate a significant increase in demand.

The development manager has insufficient resources to meet this request and has issued an invitation to potential bidders so that the development work can be outsourced.

The application must initially cover Western Europe, and later Eastern Europe, Russia, the Middle East, the Far East and Africa. A decision has yet to be made with respect to Australia, New Zealand, North and South America.

You have been asked to ensure the quality and suitability of the document sent to potential bidders and also that the application delivered by the successful bidder is ‘Tit for purpose’.

The development manager is managing the review of the responses received from bidders, and has asked the in-house test manager to provide a review checklist for the test management aspects of the responses .

Which of the following checkpoints would be appropriate? 2 credits
A . The bidder’s test policy should enforce that incident management fully conforms to IEEE 1044.
B . The bidder’s project strategy shows that the data content of all the test environments conforms to EU standards.
C . The bidder’s test plan shows that the application will be delivered for acceptance in six months time.
D . The bidder’s project test plan depicts a phased implementation with later delivery dates to be confirmed and states that test deliverables will be developed using IEEE 829 as a
guide.

Answer: D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments