Which of the following options shows the correct status?

Topic 10, Scenario 6, V3 "Independent Test Team"

Three exit criteria have been defined for the project:

– A: Test cases passed more than 70%

– B: Number of outstanding defects lest than 5

– C: Number of defects per test case less than 0.5

The first week of the testing has shown the following results:

Evaluate the status of the project against the defined exit criteria .

Which of the following options shows the correct status? 2 credits
A . Criteria A = OK, criteria B = OK, criteria C = OK
B . Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK
C . Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK
D . Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK

Answer: B