Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)

Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project. 2 credits (for 2 out of 3 correct 1 credit)
A . Test planning, test case preparation and test execution for each of the four iterations
B . Work should be explicitly allocated to test completion, test management, installation and to training on using the system
C . Activities to deploy the system in the user environment
D . Regression testing in the second, third and fourth iterations
E . Development activities for unit and integration testing
F . Reviews on requirements documentation
G . Defining test environment requirements for system testing

Answer: A,B,D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments