What should you do?

You manage a project schedule by using Project Professional 2013.You are concerned about project costs.After viewing the Cost Variance column, you realize that the project has a cost variance of $5,000.00. You need to view graphically which tasks and resources are causing the $5,000.00 cost variance. What should you do?A . View the Task Cost Overview report.B...

November 22, 2018 No Comments READ MORE +

You are a project manager who uses Project Standard 2013.Your manager wants you to plan an office move.You have a project schedule from a prior office move named “OfficeMove.mpp” and you want to use this project to assist in planning the current office move.In the fewest steps possible, you need to create your new project schedule based on the old project schedule.What should you do?

You are a project manager who uses Project Standard 2013.Your manager wants you to plan an office move.You have a project schedule from a prior office move named “OfficeMove.mpp” and you want to use this project to assist in planning the current office move.In the fewest steps possible, you need to create your...

November 12, 2018 No Comments READ MORE +

・The group resources are billed out at $140/hour.You need to add these resources to the schedule and track your project costs.Which two actions should you perform?

You work as a project manager for a construction company that uses Project Professional 2013.You have created your work breakdown structure (WBS) and are adding resources to your tasks.However, one of your tasks requires multiple resources.You have the name of the project’s lead support individual, and you have been provided with the equivalent of three full-time support resources.These three resources are not named individuals...

November 10, 2018 No Comments READ MORE +

Team members often do not work at the same time when completing their work on the tasks.You need to resolve the overallocations by using the Resource Leveling function.What should you do?

You are a project manager who uses Project Professional 2013.All resources in your project schedule have availability of 8 hours per day.You notice that several of the resources on the project are overallocated.You decide to level the project to help resolve the overallocations for the resources. Team members often do not work at the same...

November 10, 2018 No Comments READ MORE +

What should you do?

You are project manager who uses Project Professional 2013.Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project.The task list contains over 100 items.You need to create a project based on the tasks in the SharePoint list in the most efficient manner....

November 1, 2018 No Comments READ MORE +

What should you do?

You are managing a project by using Project Professional 2013. Your project schedule contains 1000 tasks which are in outline format.You discover that the Design summary task is located below the Build summary group of tasks.You need to move the Design summary task and its detail tasks to the proper location. What should you...

October 31, 2018 No Comments READ MORE +

You need to use the Baseline2 fields to calculate Variance at Completion (VAC).You have already set Baseline2.What should you do?

You manage a project by using Project Standard 2013. You need to use the Baseline2 fields to calculate Variance at Completion (VAC).You have already set Baseline2.What should you do?A . Enter physical percent complete for the tasks that have actual values.Set the Baseline to the Baseline2, and reschedule uncompleted work based on the status...

October 20, 2018 No Comments READ MORE +

You are a project manager who uses Project Professional 2013.You are planning an office move, which will occur over a weekend.You use Auto Scheduled tasks and create a weekend working calendar.You need to assign the weekend working calendar to the task.What should you do?

You are a project manager who uses Project Professional 2013.You are planning an office move, which will occur over a weekend.You use Auto Scheduled tasks and create a weekend working calendar.You need to assign the weekend working calendar to the task.What should you do?A . Click on the Task tab and select the Change Working Time button.Assign...

October 8, 2018 No Comments READ MORE +