Which two checks indicate that the cluster is ready for the replacement to be performed?

Click the Exhibit button.

You are preparing to replace a Cisco Nexus 92300YC switch. You have executed the cluster ping-cluster node1 command and received the output as shown in the exhibit.

Which two checks indicate that the cluster is ready for the replacement to be performed? (Choose two.)
A . 2 paths up, 0 paths down (TCP check)
B . 2 paths up, 0 paths down (UDP check)
C . larger than PMTU communication succeeds on 4 path(s)
D . basic connectivity succeeds on 4 path(s)

Answer: A,D