In this scenario, which two statements are true?

You have added two new AFF A250 nodes to an existing 4-node cluster with NetApp CN1610 cluster network switches. Although the nodes can join the cluster, the storage failover show command output shows that the NVRAM log is not synchronized, and it cannot reach the partner over an HA interconnect.

In this scenario, which two statements are true? (Choose two.)
A . The AFF A250 requires switches with 40GbE port support.
B . The AFF A250 uses different ports for the cluster and the HA interconnect.
C . The AFF A250 requires switches with 25GbE port support.
D . The AFF A250 uses the same port for the cluster and the HA interconnect.

Answer: B,C

Latest NS0-184 Dumps Valid Version with 60 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments