Which one of the following is not one of the three reasons why trace requirements is useful?

You are the business analyst for your organization and you are completing the manage requirements traceability process. You are tracking the requirements to determine how the requirements are interrelated with one another and with the actual delivery of the project scope.

There are actually three reasons why the business analyst should trace requirements.

Which one of the following is not one of the three reasons why trace requirements is useful?
A . Impact analysis
B . Requirements coverage
C . Requirements allocation
D . Quality control

Answer: D

Latest CBAP Dumps Valid Version with 498 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments