Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?

Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?
A . Project manager
B . Subject matter expert
C . Solution owner
D . Stakeholder

Answer: C

Latest CBAP Dumps Valid Version with 498 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments