Which of the following statements is NOT true of an Impediment Log?

Which of the following statements is NOT true of an Impediment Log?
A . Impediment Log can be discussed during Daily Standup.
B. Internal impediments from within the team are never recorded in the Impediment Log, and only brought up during the Daily Standups.
C. Transparency in Scrum ensures swift and easy identification of impediments.
D. Scrum Master maintains and updates the Impediment Log.

Answer: B

Explanation:

Reference: http://blog.scrumstudy.com/scrumstudy-scrum-video-on-daily-standup-meeting-and-its-importanceto-a-scrum-team/