Mark is the Product Owner and he asks you, the Scrum Master what burndown charts actually track.
What’s the best response for Mark?
A . Burndown charts will track the remaining work across the project time.
B. Burndown charts will track the value of the work performed by the Development Team.
C. Burndown charts will track work still left in the project.
D. Burndown charts will track the cost of the work.
Answer: A