What should the Scrum Master do with newly identified issues or bugs?

A team has some trouble managing issues and bugs. They decide to track them using the team’s Scrum board. They plan some time in every sprint to deal with important issues and bugs

What should the Scrum Master do with newly identified issues or bugs?
A . Ask the Product Owner to move them to the product backlog and ignore them for now
B. Assign them as tasks to the Developers as soon as the issues and bugs are identified
C. Call a meeting for the Developers and have them discuss the correct priority and actions
D. Have the Product Owner assess the priority and move them to the appropriate backlog

Answer: C

Latest ASM Dumps Valid Version with 39 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments