Which of the following should be the project manager’s NEXT steps?

A vendor is unable to deliver an order by the specified date.

Which of the following should be the project manager’s NEXT steps? (Choose two.)
A . The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B . The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
C . The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
D . The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
E . The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.

Answer: A,D

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Leave a Reply

Your email address will not be published.

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>