Which of the following will MOST likely be impacted by the changes?

A company has dictated project scope changes but has stated that the original budget still applies.

Which of the following will MOST likely be impacted by the changes?
A . Quality
B . Regulations
C . Schedule
D . project team

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133