If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?

If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
A . The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B . The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
C . The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
D . The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.

Answer: B

Latest PK0-004 Dumps Valid Version with 574 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments