A project has been experiencing some difficulties due to third-party vendors. The project manager should request.

A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
A . Additional resources
B . A gate review
C . A risk register update
D . A performance audit

Answer: C

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 272