Warning: Undefined variable $in_footer in /var/www/html/exam4training.com/wp-content/themes/ultra-child/functions.php on line 14
Which of the following is the NEXT step? - Exam4Training

Which of the following is the NEXT step?

A project manager is justifying a required change with the associated impact on the project.

Which of the following is the NEXT step?
A . Implementation
B . Approval
C . Validation
D . Auditing

Answer: B

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 294