How should the project manager reply?

At the end of a project’s initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?
A . Recurrent team meetings are planned to control the budget against future uncertainties.
B. Probabilistic analysis was used to develop the budget to address future uncertainties.
C. The budget was developed by using the lessons learned from previous project data.
D. Feedback from stakeholders will be addressed at each board meeting to adapt the budget.

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments