How should the project manager communicate the design to the implementation team?

A project team is completing a design, while another team in a different country is performing implementation.

How should the project manager communicate the design to the implementation team?
A . Send a detailed email with the completed design document.
B. Conduct a workshop with all of the stakeholders.
C. Conduct a workshop with both of the teams.
D. Upload the design documents into the project repository.

Answer: C

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments