Which of the following should the project manager do to resolve this issue?

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client. Which of the following should the project manager do to resolve this issue?A . Update the scope management plan.B . Modify the project baselines.C...

July 31, 2022 No Comments READ MORE +

In which of the following organizational structures would a project manager have the MOST authority?

In which of the following organizational structures would a project manager have the MOST authority?A . ProjectizedB . Strong matrixC . Balanced matrixD . FunctionalView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 57

July 31, 2022 No Comments READ MORE +

Which of the following documents would determine the contractual obligations?

A company hires an outside vendor to provide 24/7 support. Which of the following documents would determine the contractual obligations?A . POB . SLAC . LOID . MOUView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303

July 30, 2022 No Comments READ MORE +

Which of the following documents should the project coordinator use?

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator use?A . Risk registerB . Issue logC . Communication planD . Status reportView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA...

July 30, 2022 No Comments READ MORE +

Which of the following is the MOST likely reason?

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change. Which of the following is the MOST likely reason?A . Established communication planB . Scope creepC . Resource constraintsD . Iterative approachView AnswerAnswer: B...

July 30, 2022 No Comments READ MORE +

Which of the following documents should the project manager create?

A project manager is assigned to a new project that must start immediately. No formal or approved documents have been authored for the project. The project manager must identify project roles, justify the business need, and determine project scope boundaries. Which of the following documents should the project manager create?A...

July 29, 2022 No Comments READ MORE +

Which of the following should a project manager update to document this information?

A team lead informs the project manager that the datacenter will not be accessible when the project needs to be completed. The team lead also indicates that the team member who is assigned to complete the datacenter project is out on medical leave. Which of the following should a project...

July 29, 2022 No Comments READ MORE +

Which of the following should the project manager do NEXT?

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?A . Gain approval for the changes.B . Identify the approval authority.C . Implement the changes.D . Create an...

July 28, 2022 No Comments READ MORE +

Which of the following meetings should be held to move to the NEXT step in the project?

The client accepts the critical design review. Which of the following meetings should be held to move to the NEXT step in the project?A . ExecutionB . KickoffC . ClosureD . PlanningView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 112

July 28, 2022 No Comments READ MORE +

Which of the following is the BEST step for the project manager to take?

A senior manager asks a project manager for an estimated budget on a new project. Which of the following is the BEST step for the project manager to take?A . Tell the senior manager the estimation is not available yet.B . Use the budget from a similar project to generate...

July 28, 2022 No Comments READ MORE +