Which of the following documents should the project team reference to fast-track the project?

A program manager informs a project manager that a new, high-priority project has been approved and will need the current project’s resources before the scheduled project close date. The project team meets and determines that the project should be fast-tracked. Which of the following documents should the project team reference...

August 2, 2022 No Comments READ MORE +

Which of the following documents would a project manager create to make team meetings more effective?

Several team members report that meeting objectives are not being met. Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)A . Create an SOW prior to each meeting and adhere to it.B . Create a meeting agenda prior to each meeting...

August 2, 2022 No Comments READ MORE +

Which of the following is a schedule that illustrates the duration of an activity?

Which of the following is a schedule that illustrates the duration of an activity?A . Process diagramB . Ishikawa diagramC . Gantt chartD . Pareto chartView AnswerAnswer: C Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168

August 2, 2022 No Comments READ MORE +

Which of the following types of organizational change is described?

A company is hired to perform some of another organization’s work. Which of the following types of organizational change is described?A . OutsourcingB . Business process changeC . Shared resourcesD . SplitView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297

August 1, 2022 No Comments READ MORE +

Which of the following documents would contain these items?

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?A . Business caseB . Requirements documentC . Project timelineD . Task planView AnswerAnswer: B Explanation: References: Kim Heldman, CompTIA Project+...

August 1, 2022 No Comments READ MORE +

Which of the following is the MOST cost-effective step to take to ensure the project’s success?

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?A . Reduce the scopeB . Increase the budgetC . Decrease staffD . Update the WBSView AnswerAnswer: D Explanation: References: https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false

August 1, 2022 No Comments READ MORE +

To alter the pace of the project, which of the following should the project manager do FIRST?

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date. To alter the pace of the...

August 1, 2022 No Comments READ MORE +

Which of the following activities are associated with the closing phase of a project? (Choose two.)

Which of the following activities are associated with the closing phase of a project? (Choose two.)A . Risk mitigationB . Archiving of project documentsC . Tracking of expendituresD . Lessons learnedE . Quality assuranceView AnswerAnswer: B,D Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p....

August 1, 2022 No Comments READ MORE +

Which of the following phases does this describe?

A project manager is working on the project charter. Which of the following phases does this describe?A . InitiationB . PlanningC . ExecutionD . ClosingView AnswerAnswer: A Explanation: References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 107

August 1, 2022 No Comments READ MORE +

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?

Which of the following individuals is MOST likely to be a key stakeholder for the product launch phase of a project?A . Sales clerkB . Marketing representativeC . Team leadD . Product itemView AnswerAnswer: B

July 31, 2022 No Comments READ MORE +