Which one of the following statements is NOT TRUE regarding Impediment Logs?

George is a Scrum Master on a project to develop a Course Management System and Leave Management System for Greyward University. He is maintaining an Impediment Log.

Which one of the following statements is NOT TRUE regarding Impediment Logs?
A . An impediment is any hindrance or hurdle that reduces the productivity of the Scrum Team.
B. Impediments can be internal or external to the team.
C. The Impediment Log must be shared with the stakeholders.
D. Impediments should be formally recorded by the Scrum Master in an Impediment Log.

Answer: C

Explanation:

Reference: http://blog.scrumstudy.com/scrumstudy-scrum-video-on-daily-standup-meeting-and-its-importanceto-a-scrum-team/