What should Marty tell the Development Team regarding the completeness of a Product Backlog?
Marty is coaching the Development Team on being completely done with the user stories in a Sprint.
What should Marty tell the Development Team regarding the completeness of a Product Backlog?
A . The item is done when the item has no work remaining to be released.
B. The item is done when the product customer accepts the item.
C. The item is done when the Product Owner agrees that the item can be released.
D. The item is done when the Scrum Master agrees it is complete.
Answer: A