Which one of the following is an output of Sprint Planning and is used to give the Development Team a Sprint target?
Which one of the following is an output of Sprint Planning and is used to give the Development Team a Sprint target?
A . Sprint Goal
B. Roles and Responsibilities
C. Product Backlog
D. Team charter
Answer: A