What is the greatest advantage of having 3 Sprints of 2 weeks?
A Scrum Team suggests to have a project with 3 Sprints of 2 weeks, while the customer suggests 1 Sprint of 6 weeks.
What is the greatest advantage of having 3 Sprints of 2 weeks?
A . The customer has to invest fewer time.
B. The team can inspect and adapt 2 times.
C. The team delivers more Story Points.
Answer: C