Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?

Who must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design?
A . The general contractor
B . A LEED AP
C . The project’s mechanical engineer
D . The owner or an owner’s representative

Answer: D

Explanation:

According to the LEED v4: Building Design + Construction Guide, the owner or an owner’s representative must be a member of the integrated project team for the Integrative Process Prerequisite, Integrative Project Planning and Design. The owner or an owner’s representative is responsible for establishing the project’s vision, goals, budget, and schedule, as well as defining the owner’s project requirements (OPR) and participating in the design charrettes and reviews1. The owner or an owner’s representative also plays a key role in ensuring the continuity and alignment of the project’s performance and environmental objectives throughout all phases of the project1.

The other choices are not mandatory members of the integrated project team, although they may be involved in the integrative process depending on the project’s scope and needs. The general contractor is typically hired after the design phase and may not be involved in the predesign and schematic design analyses required by the prerequisite1.A LEED AP is a professional who has demonstrated knowledge and experience in applying the LEED rating system, but is not required to be part of the integrated project team, although it is recommended and rewarded by the LEED credit, Integrative Process1. The project’s mechanical engineer is one of the possible design consultants who may contribute to the integrative process, especially for the energy-related systems analysis, but is not required to be part of the integrated project team1.

References: LEED v4: Building Design + Construction Guide, Integrative Process Prerequisite, Integrative Project Planning and Design, Requirements1