Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?

Which of the following project team members should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning?
A . Owner
B . Contractor
C . Occupants
D . Facility manager

Answer: B

Explanation:

Contractor

The contractor is the project team member who should be integrated early into the design phase to assist with earning the Materials and Resources Prerequisite, Construction and Demolition Waste Management Planning. The contractor is responsible for implementing the waste management plan, which includes estimating the types and quantities of waste materials, identifying the diversion strategies, selecting the waste haulers and recyclers, tracking and documenting the waste diversion performance, and training the subcontractors and workers. The contractor can provide valuable input on how to reduce, reuse, and recycle the construction and demolition waste, as well as identify potential challenges and opportunities for achieving the prerequisite requirements.

References:

Reference Guide for Building Design and Construction v4 C Pages 263-2641