What is a benefit of including the public in a charrette for a new school before the pre-design phase?

What is a benefit of including the public in a charrette for a new school before the pre-design phase?
A . Neighbors can plan for future construction
B . It will help streamline the permitting process
C . Potential partnerships with the community can be revealed
D . The owner can determine financial strategies based on the public’s input

Answer: C

Explanation:

A charrette is a collaborative design process that involves multiple stakeholders, such as the owner, the design team, the community, and the users. By including the public in a charrette for a new school before the pre-design phase, potential partnerships with the community can be revealed. For example, the school might share facilities or resources with a nearby library, park, or community center. This can enhance the social and environmental benefits of the project, as well as reduce costs and increase efficiency.

References: LEED BD+C Reference Guide, Introduction, page 171; LEED BD+C Reference Guide, Integrative Process, page 291