For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include

For Location and Transportation Credit, Access to Quality Transit, a project team preparing timetables and service-level documentation must ensure the materials include
A . verification that a weighted daily average has been used for each qualifying route
B . confirmation that functional entries of the project are within 3/4 mi. (1.20 km) of the stop
C . verification that a weighted building average has been used for each qualifying functional entry
D . confirmation that each qualifying route features paired route service (service in opposite directions)

Answer: A

Explanation:

This option requires the project team to calculate the weighted daily average of the number of trips per day for each qualifying route, using the formula provided in the LEED v4: Building Design + Construction Guide. This option ensures that the transit service frequency is accurately represented and meets the minimum thresholds for weekday and weekend trips, as shown in Table 1 and Table 2 of the guide.

References: = [LEED v4: Building Design + Construction Guide], Access to Quality Transit.