Which stakeholder would need detailed technical interface requirements?

You are the business analyst for the NHQ Project. You have identified several stakeholders that need different types of information related to the requirements.

Which stakeholder would need detailed technical interface requirements?
A . Project manager
B . Testers
C . Implementation subject matter experts
D . Regulators

Answer: C

Explanation:

The implementation subject matter experts will need requirements that provide detailed interface requirements, so that they may construct the solution. They are responsible for designing and implementing potential solutions. Implementation subject matter experts will provide specialist expertise on the design and construction of the solution components.

Answer. A is incorrect. The project manager will need requirements in an easy to understand format, so that he may create the project scope.

Answer. D is incorrect. Regulators may have specific legal, contractual, or governance requirements regarding what is included in a requirements document.

Answer. B is incorrect. Testers focus on understanding the critical success factors based on the needs of the business users.