When should John and Hanna perform these verification activities?

John and Hanna are business analysts in their organization and they are completing the verification activities to check for completeness of the requirements.

When should John and Hanna perform these verification activities?
A . At each milestone of the requirements analysis process
B . Once all of the requirements have been gathered
C . Iteratively throughout the requirements analysis process
D . As often as the requirements management plan calls for

Answer: C

Explanation:

Requirements verification activities are performed iteratively throughout the requirements analysis process.

Answer. A is incorrect. Requirements verification happens in iterations, not just at milestones (assuming there are milestones in the process).

Answer. B is incorrect. Verification activities don’t happen just at the end of the requirements gathering process, but iteratively throughout the process.

Answer. D is incorrect. This answer is tempting, but it’s not the best answer.