Which of the following statements best describes the change-driven approach?

You are the business analyst for your organization. On your current project you’ll be using the change-driven approach for defining requirements and gathering feedback.

Which of the following statements best describes the change-driven approach?
A . The change-driven approach favors defining requirements through experimentation.
B . The change-driven approach favors defining requirements standardized templates.
C . The change-driven approach favors defining requirements through team interaction.
D . The change-driven approach does not define the requirements until after a solution for the problem has been identified.

Answer: C

Explanation:

The change-driven approach looks to create business value in short iterations. The downside of this approach, however, is that there is more risk and uncertainty in the overall direction. The change-driven approach relies on team interaction to define requirements and gather feedback on the solution.

Answer. B is incorrect. The plan-driven approach relies on standardized templates, not the change-driven approach.

Answer. A is incorrect. This is not a valid description of the change-driven approach.

Answer. D is incorrect. Requirements may evolve through the change-driven approach, but they are still identified early in the business analysis work. The requirements must be identified so that the business analysts know what solution would satisfy the requirements.

Latest CCBA Dumps Valid Version with 421 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments