Which process involves developing an approximation of the monetary resources needed to complete project activities?
Which process involves developing an approximation of the monetary resources needed to complete project activities?
A . Estimate Costs
B. Control Costs
C. Determine Budget
D. Plan Cost Management
Answer: A