The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:
A . Work packages.
B. Accepted deliverables.
C. The WBS dictionary.
D. The scope baseline.

Answer: A