Which grid shows which resources are tied to work packages?

Which grid shows which resources are tied to work packages?
A . Work breakdown structure (WBS)
B. Responsibility assignment matrix (RAM)
C. Project assignment chart
D. Personnel assignment matrix

Answer: B

Latest CAPM Dumps Valid Version with 1089 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments