Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?

Which item is an output of Plan Quality Management and an input to Perform Quality Assurance?
A . Organizational process updates
B. Quality metrics
C. Change requests
D. Quality control measurements

Answer: B

Latest CAPM Dumps Valid Version with 1089 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments