Which option should you enable on the ticket template to avoid creation of multiple tickets?

A maintenance plan is created with the condition "Every 5 weeks". Based on this condition, a ticket is created on March 1, but ticket processing is delayed.

Which option should you enable on the ticket template to avoid creation of multiple tickets?
A . Consider ticket resolved on date
B . Consider contract status
C . Consider maintenance plan condition
D . Consider delay

Answer: A

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments