Which of the following is true about the "cone of uncertainty"? (Choose the best answer)

Which of the following is true about the "cone of uncertainty"? (Choose the best answer)
A . It helps to identify whether to adjust the quality, scope, or time, similar to the "Iron Triangle" of development.
B . It is used to identify the level of performance between individual team members.
C . It can help a Product Owner estimate how much work is likely to be done during a certain number of Sprints.
D . It helps a person identify gaps in his/her skills as a Product Owner.

Answer: C