What is the Product Owner accountable for in Sprint 0? (Choose the best answer)

What is the Product Owner accountable for in Sprint 0? (Choose the best answer)
A . Form Scrum Teams that are able to deliver on commitments.
B . Finalizing project requirements in order to input into the Product Backlog.
C . There is no such thing as Sprint 0.
D . Plan the roadmap for the next 3 Sprints.

Answer: C