How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint? (Choose the best answer)

How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint? (Choose the best answer)
A . Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
B . Enough time for the last Increment to finish testing.
C . All of the above are allowed.
D . None. A new Sprint starts immediately following the conclusion of the previous Sprint.
E . Maximum of 1 day for Sprints that are time-boxed to 2 weeks.

Answer: D