Which is an appropriate response if there are unfinished items in the Sprint Backlog by the end of the Sprint time-box? (Choose the best answer)

Which is an appropriate response if there are unfinished items in the Sprint Backlog by the end of the Sprint time-box? (Choose the best answer)
A . The Sprint time-box holds and the Scrum Team continuously learns what is actually possible to do within a time-box and adapts.
B . The Sprint extends until all items are completed.
C . Immediately transition to Kanban.
D . The current time-box is adjusted and all future Sprints will comply to the new time-box.

Answer: A

Latest PSPO-III Practice Questions with 65 Q&As

Updated Study Material | Instant Download | Detailed Answers and Explanations

Subscribe
Notify of
guest
0 Comments