Which document you use to inform the new program manager about his responsibilities in the portfolio?

One of your component managers has submitted his resignation and left the company; a new program manager joins the portfolio replacing him .

Which document you use to inform the new program manager about his responsibilities in the portfolio?
A . Program Business Case
B . Portfolio Roadmap
C . Portfolio Management Plan
D . Portfolio Charter

Answer: C