Which document do you, as a portfolio manager, update to reflect the change to the timeline?

Your company got recently acquired by another company and the strategic directions which your portfolio is based on have been changed .

Which document do you, as a portfolio manager, update to reflect the change to the timeline?
A . Communication Management Plan
B . Portfolio Management Plan
C . Portfolio Strategic Plan
D . Portfolio Roadmap

Answer: A