You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are currently developing the strategic plan. Upon finishing it, you are expected to present

You have been recently assigned to manage a new portfolio that is supposed to shift the company from silo-based to a projectized one. You are in the process of initiating the portfolio. You are currently developing the strategic plan. Upon finishing it, you are expected to present
A . Portfolio Strategic Plan and Portfolio Process Assets updates
B . Portfolio Strategic Plan and Portfolio
C . Portfolio Strategic Plan
D . Portfolio Strategic Plan and Inventory of Work

Answer: B