During a portfolio review meeting, the steering committee has decided on the inclusion of a new project to re-align the portfolio with its strategic objectives, what do you do before and after the meeting?

During a portfolio review meeting, the steering committee has decided on the inclusion of a new project to re-align the portfolio with its strategic objectives, what do you do before and after the meeting?
A . Update the decision; write the Minutes Of Meeting
B . Change request; communicate the decision to all stakeholders in the portfolio
C . Write the Minutes Of Meeting; update the decision
D . Change request; communicate the decision to related stakeholders listed in the communication management plan

Answer: D