Where should the program manager document this?
A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment
Where should the program manager document this?
A . Program governance plan
B. Program requirements
C. Component test plan and test cases
D. Program quality management plan
Answer: A