What should the program manager do?

Several issues are identified on one component project in a program During a meeting with that component’s project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule

What should the program manager do?
A . Join project-level issue resolution meetings to accelerate the decision-making process.
B. Initiate discussions with the program governance board about assigning a more experienced project manager to the project
C. Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting
D. Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilities

Answer: D

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments