When does the Nexus Sprint Planning end?

When does the Nexus Sprint Planning end?
A . When the expected results of the Nexus Sprint Planning are met
B. When all the individual teams finish their Sprint Planning
C. When the Product Owner says so
D. When the representatives of each team meet after the individual teams’ Sprint planning

Answer: A

Explanation:

The Nexus guide no longer prescribes the format of the Nexus Sprint Planning. Instead, it states the purpose and the expected results of the event. This event ends when all the expected results are achieved.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments