What is Nexus Sprint Backlog used for? Select all that apply.

What is Nexus Sprint Backlog used for? Select all that apply.
A . It is used to highlight dependencies
B. It is used to track the progress of the Nexus Integration Team
C. It is used to highlight the progress of the team
D. It is used to highlight flow of work

Answer: A,D

Explanation:

Nexus Sprint Backlog is used to highlight dependencies and the flow of work during the Sprint.