What can be the result of this?

Teams want to integrate the code only before the Nexus Sprint Review.

What can be the result of this? Select all that apply.
A . There may be too many code conflicts while integration
B. It will save Nexus members time
C. There may be too little time to resolve integration issues
D. Integrated Increment may not be available in time

Answer: A,C,D

Explanation:

Work performed by the teams must be integrated often and should not be postponed until Nexus Sprint Review. It is common for teams to face integration issues even when they integrate the code daily. But they will have time to resolve the issues.