Nexus Integration team has defined a Definition of Done with 5 point criteria. One of the Sprint Team, want to use only 3 of them for their team’s Definition of Done. Is this allowed?

Nexus Integration team has defined a Definition of Done with 5 point criteria. One of the Sprint Team, want to use only 3 of them for their team’s Definition of Done. Is this allowed?
A . No
B. Yes

Answer: A

Explanation:

Individual Scrum Teams may choose to apply a more stringent definition of Done within their own teams, but cannot apply less rigorous criteria than agreed for the Increment.

Latest SPS Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments